UDCPR 2020 / Chapter 10, City specific regulations

10.3.6 Generation of TDR

UDCPR 2020 as amended to 30.01.2025

For encumbered plots which are required for implementation of public purpose on urgent basis, following shall be applicable :-

(i) In case of land which were /are fully encumbered and where encumbrances had / have to be removed and / or rehabilitated by the project implementing authority, TDR / DRC shall be issued equivalent to the area of land taken over for free public project.

(ii) In case of land which were / are partly encumbered and where encumbrance are / were rеmoved and / or rehabilitated elsewhere by the project implementing authority, the entitlement for TDR / DR for the portion of land which is / was vacant shall be as per Sr.No.(a) of Regulation 11.2.4 and the entitlement of TDR / DRC for the portion of land which is / was encumbered shall be equivalent to the area of encumbered land taken over for public project. However, before permitting / granting TDR / DRC for encumbered land, project implementing authority shall separately certify the area of land which are vacant and the area of land under encumbrance alongwith detail as per the joint measurement survey carried out in this respect with the city survey officer. The area of vacant land and land under part encumbrance shall be clearly distinguished and demarcated, otherwise the land under part encumbrance shall be treated as fully encumbered land.

To see how 10.3.6 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.

The text of the Unified Development Control and Promotion Regulations for Maharashtra State, as amended to 30.01.2025. The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.