UDCPR 2020 / Chapter 14, Special schemes
14.1.1.14 Transition Policy
UDCPR 2020 as amended to 30.01.2025
i) It shall be permissible for the Project Proponent/s, to whom Special Township Project (1)ITP as per earlier Regulations has already been granted location clearance and / or LOI or the project is on-going wherein part Occupancy Certificate is granted (1) as per then prevailing Regulation before coming in to force of this Regulation. -
(1) Modified vide Notification u/s.37(1AA)(c) & 20(4) bearing No.CR.105/2022/(Part-2)/UD-13, dt.05th September, 2024
a) Continue such Special / Integrated Township Project under the erstwhile regulations under which LC is granted without considering these regulations.
b) If the project proponents wish to develop township according to this regulations then he may apply for grant of (1) revised Locational Clearnce from State Government as per Regulation No.14.1.1.4 alongwith the additional documents mentioned at Sr.No.(j) therein.
ii) If in case as described in Regulation No.14.1.1.14(i)(b), the construction of the project is on-going and the Occupation Certificate, either in fully or partly has granted or not been granted, it shall be permissible for the Project Proponent/s to choose an option to prefer this regulation subject to payment of premium as prescribed in Regulation No.14.1.1.7(i) and (ii). In such cases premium shall be calculated on balance area which shall be the difference of FSI permitted as per earlier regulation and that being availed as per this regulation.
To see how 14.1.1.14 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
UDCPR 2020, 14.1.1.14, as amended to 30.01.2025. https://citiwise.in/udcpr/14-1-1-14
Source
These words are UDCPR 2020 as the Directorate of Town Planning, Government of Maharashtra, publishes it in its consolidated text, as amended to 30.01.2025 with earlier provisions and corrections. 14.1.1.14 is printed on pages 264 to 265 of that text. Read the official text (PDF).
The amendments noted beside these words in the official text:
- Modified vide Notification u/s.37(1AA)(c) & 20(4) bearing No.CR.105/2022/(Part-2)/UD-13, dt. 05th September, 2024.
The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.