UDCPR 2020 / Chapter 14, Special schemes

14.8.10 Selection of Implementation Agency –

UDCPR 2020 as amended to 30.01.2025

If an owner or group of owners or proposed co-op. Hsg. Society of occupants or federation of occupants, either directly or through a Power of Attorney Holder, collectively owning more than

(1) 51% of the area of URC or a part thereof, come forward for implementation of URS as per the Detailed Plan prepared by the Commissioner for such URC, within 3 months of declaration of the detailed plans of URC, or within such extended period as may be granted by theCommissioner, they may be selected as Implementation Agency for implementation of URS on such URC. In such a case (2) the infrastructure should be developed by the Implementing Agency at their own cost, otherwise an Infrastructural charges at the rate of 10% of construction

(2) cost of buildings of rehab & free sale component (excluding infrastructure) as per prevailing ASR to be received by the corporation. In case owners / stakeholders owning more than 51% of whole or part area of URS as mentioned above fail to come together, selection of an implementation agency for the URS shall be done through a transparent bid process.

To see how 14.8.10 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.

The text of the Unified Development Control and Promotion Regulations for Maharashtra State, as amended to 30.01.2025. The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.