UDCPR 2020 / Chapter 2, Development permission and commencement certificate
2.2.14 Premium Charges and Fire Infrastructure Charges.
UDCPR 2020 as amended to 30.01.2025
i) Premium Charges - Premium charges as may be required to be recovered under these regulations shall be paid to the Authority before issue of development permission / commencement certificate. The 50% Premium share of the Government shall be deposited by the Authority in a specified head of account of the Government. The amount of premium collected by the Authority shall be kept in a separate account and it shall be utilized for development of civic amenities and infrastructure. In case of Regional Plan area, 100% premium charges shall be paid to Government through the District offices of Town Planning and Valuation Department. The aforesaid premium chargesexcept the premium leviable under Chapter 5 of these regulations shall be allowed to be paid in the instalments with interest @ 8.5% per annum in the following manner and subject to following conditions.
(1) Inserted vide Corrigendum / Addendum No.CR.121/21, dt.02nd December, 2021
(#) Clarifications issued vide letter CR.42/21/UD-12, dt.14th June, 2021 & CR.236/18 (Part 2), dt.23rd December, 2021
A) Option - 1
a) Building below 70.0 m. height. Initial At the end of Month with interest
Payment 12 th
24th 36th 48th
1stInstalment 2nd Instalment 3rd Instalment 4th Instalment 5th Instalment
10% 22.5% 22.5% 22.5% 22.5%
b) Building having height of 70.0 m. and above.
Initial At the end of Month with interest
Payment 12 th
24th 36th 48th 60th
1st Instalment 2nd 3rd 4th 5th 6th
Instalment Instalment Instalment Instalment Instalment
10% 18% 18% 18% 18% 18%
B) Option - 2 The instalment of 20% shall be paid at the time of granting development permission / commencement certificate and remaining 80% amount at the time of occupation certificate. The remaining amount shall be liable for interest @ 8.5% per annum.
Notes :
i) The instalment shall be granted with the interest at the rate of 8.5% p.a. on reducing outstanding balance premium.
ii) The owner / developer shall deposit post-dated cheques for instalment amount with an interest due drawn on scheduled bank, as per the scheduled date of payment.
iii) Occupation Certificate shall be granted in proportion to the payments made.
iv) The first instalment shall not be less than 50 lakhs in case of A, B, C Class Municipal Corporations and 25 lakhs in case of other areas. (2) However the Planning Authority may reduce the first instalment limit as a policy by considering local conditions. (2) In such case, the remaining amount shall be apportioned in remaining instalments.
(2)
v) (Deleted). (2)
(#)
ii) Fire Infrastructure Charges - These charges shall be decided by the Government from time to time
To see how 2.2.14 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
The text of the Unified Development Control and Promotion Regulations for Maharashtra State, as amended to 30.01.2025. The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.