The plans of the buildings and elevation and section to be sent with the application accompanying the notice shall be drawn to a scale of 1:100. The building plan shall :
i) Include floor plans of all floors together with the built up area clearly indicating the sizes of rooms and the position and width of staircase, ramps and other exit ways, lift wells, lift machine room and lift pit details, meter room and electric sub-station and also include ground floor plan as well as basement plan and shall indicate the details of parking space and loading and unloading spaces provided around and within the building as also the access ways and the appurtenant open spaces with projections in dotted lines, distance from any building existing on the plot in figured dimensions along with accessory building. These plans will also contain the details of FSI calculations;
ii) Show the statement of carpet area of every apartment or any unit along with areas of balconies and double height terraces, if any, attached to the said unit;
iii) Show the use or occupancy of all parts of the buildings;
iv) Show exact location of essential services, such as water closet (W.C.), bath, sink and the like;
v) Include sectional drawings showing clearly the thickness of basement wall, wall construction, size and spacing of framing members, floors, slabs, roof slabs with the materials. The section shall indicate the height of the building, rooms and parapet, drainage and slope of the roof. At least one section should be taken through the staircase;
vi) Show relative levels of street;
vii) Give dimensions of the projected portion beyond the permissible building line;
viii) Include terrace plan indicating the drainage and the slope of the roof;
ix) Give indication of the north line relative to the plan;
x) Details of parking spaces provided;
xi) Give dimensions and details of doors, windows and ventilators;
xii) Give the area statement with detailed calculation chart of each floor of the building or area as per periphery line of construction (P-line) excluding ducts and voids;
xiii) Show the pump rooms, rain water harvesting system, sewage treatment plant, if any;
xiv) Certificate of Structural Engineer about structural and earthquake safety in case of building above G + 2 or stilt + 2 structure;
xv) Give such other particulars as may be required to explain the proposal clearly as prescribed by the Authority.
(#)