UDCPR 2020 / Chapter 2, Development permission and commencement certificate
2.8.5 Deviation During Construction
UDCPR 2020 as amended to 30.01.2025
If during construction of a building, any deviation of a substantial nature from the sanctioned plans is intended by way of internal or external additions, sanction of the Authority shall be necessary. A revised plan showing the deviation shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Authority, shall be deemed as un-authorised. However, any changes made within the internal layout of a residential or commercial unit, which do not violate FSI or other regulations, shall not be treated as unauthorised. Such changes shall be incorporated in plan along with completion certificate. Provided that revised permission may also be granted after completion of work before obtaining full occupancy certificate.
To see how 2.8.5 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
UDCPR 2020, 2.8.5, as amended to 30.01.2025. https://citiwise.in/udcpr/2-8-5
Source
These words are UDCPR 2020 as the Directorate of Town Planning, Government of Maharashtra, publishes it in its consolidated text, as amended to 30.01.2025 with earlier provisions and corrections. 2.8.5 is printed on page 37 of that text. Read the official text (PDF).
The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.