3.1.12 Distance from Natural Lake and Dam

UDCPR 2020 as amended to 30.01.2025

In Regional Plan area, no construction shall be allowed within 100 m. from the high flood line of natural lake. In Development Plan area, development around natural lake shall be governed by the provisions made in such plan. In absence of the provisions in such plan the distance as may be specified by Irrigation Department shall be followed. The regulation regarding clear distances from the High flood line while carrying out any development of any land around dam and foothill areas as notified and the norms regarding distance as prescribed in Government of Maharashtra, Water Resources Department Marathi Circular No.संनकणग -2012/(प्र.क्र.20/2012) सस.व्य.(महसूल), dt.08/03/2018 and amendments therein, from time to time, will be applicable henceforth, subject to following condition. Condition :- The concerned land owners/users are prohibited to discharge any Garbage / Water Sewage / Wastage in the reservoir, generating from its premises. It will be compulsory and binding on the land owner / user to make necessary arrangements within the premises for Water and sewage disposal management and to maintain the Zero Discharge condition at his own cost.

To see how 3.1.12 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.

UDCPR 2020, 3.1.12, as amended to 30.01.2025. https://citiwise.in/udcpr/3-1-12

Source

These words are UDCPR 2020 as the Directorate of Town Planning, Government of Maharashtra, publishes it in its consolidated text, as amended to 30.01.2025 with earlier provisions and corrections. 3.1.12 is printed on page 42 of that text. Read the official text (PDF).

The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.