UDCPR 2020 / Chapter 3, General land development requirements
3.1.4 Development within 30.0 m. Distance from Railway Boundary
UDCPR 2020 as amended to 30.01.2025
For any construction within 30.0 m. from railway boundary, No Objection Certificate from Railway Authority shall be necessary.
To see how 3.1.4 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
UDCPR 2020, 3.1.4, as amended to 30.01.2025. https://citiwise.in/udcpr/3-1-4
Source
These words are UDCPR 2020 as the Directorate of Town Planning, Government of Maharashtra, publishes it in its consolidated text, as amended to 30.01.2025 with earlier provisions and corrections. 3.1.4 is printed on page 41 of that text. Read the official text (PDF).
The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.