UDCPR 2020 / Chapter 3, General land development requirements

3.6 Provision for electric sub-station

UDCPR 2020 as amended to 30.01.2025

In case of development / re-development of any land, building or premises mentioned below, provision for electric sub-station shall be made as under, if the requirement for the same is considered necessary by the concerned power supply authority.

     Sr. No.              Plot Area                             Maximum requirements
        1      Plot above 2000 sq.m.                  One single transformer sub-station of the size

of 5.0 m. x 5.0 m. and height of not more than 5.0 m.

       2       Layout or sub-division of a plot       A suitable site for an electric sub-station as
               measuring 2 .0 ha. or more.            required by the Power Supply Company.

Provided that the sub-station is constructed in such a manner that it is away from main building at a distance of at least 3.0 m. and in general does not affect the required side marginal distances or prescribed width of internal access or recreational open space.

To see how 3.6 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.

UDCPR 2020, 3.6, as amended to 30.01.2025. https://citiwise.in/udcpr/3-6