UDCPR 2020 / Chapter 7, Higher FSI for certain uses
7.4.6 Development / redevelopment of housing schemes of maharashtra housing and area development authority
UDCPR 2020 as amended to 30.01.2025
i) For providing the requisite infrastructure for the increased population, an infrastructure charge at the rate of 7% of the Land Rate as per the ASR of the year of approval of the redevelopment project shall be chargeable for the extra FSI granted over and above the basic FSI admissible for the redevelopment schemes. 50% of the Infrastructure Charge levied and collected by MHADA shall be transferred to the Authority for developing necessary off site infrastructure.
ii) No premium shall be charged for the FSI admissible as per the prevailing regulations.
a) Construction of EWS / LIG and MIG tenements by MHADA on a vacant plot, or
b) In a redevelopment project for the construction of EWS / LIG and MIG tenements towards the share of MHADA.
To see how 7.4.6 and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
UDCPR 2020, 7.4.6, as amended to 30.01.2025. https://citiwise.in/udcpr/7-4-6
Source
These words are UDCPR 2020 as the Directorate of Town Planning, Government of Maharashtra, publishes it in its consolidated text, as amended to 30.01.2025 with earlier provisions and corrections. 7.4.6 is printed on page 133 of that text. Read the official text (PDF).
The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.