UDCPR 2020 / Chapter 7, Higher FSI for certain uses
Table 7-C Where redevelopment of buildings in existing housing schemes of MHADA (7.4.2)
UDCPR 2020 as amended to 30.01.2025
Table No.7-C
Basic Ratio (LR / RC) Incentive (As % of Admissible Rehabilitation Area)
Above 6.00 40%
Above 4.00 and up to 6.00 50%
Above 2.00 and up to 4.00 60%
Up to 2.00 70%
Explanation :-
* RC is the rate of construction in respect of R.C.C. Construction, as published by the Chief
Controlling Revenue Authority & Inspector General of Registration, Maharashtra State in the
Annual Statements of Rates.
Provided that the above incentive shall be subject to the availability of the FSI on the Plot
under redevelopment and its distribution by MHADA.
Provided further that in case there are more than one land rate applicable to different parts of
the plot under redevelopment, a weighted average of all applicable rates shall be taken for
calculating the Average Land Rate and the Basic Ratio.
Provided further that the Land Rate (LR) and the Rate of Construction (RC) for calculation of
the Basic Ratio shall be taken for the year in which the redevelopment project is approved by
the authority competent to approve it.
iii) Sharing of the Balance FSI :- The FSI remaining in balance after providing for the
rehabilitation and the incentive components, calculated as per (i) and (ii) above respectively,
shall be shared between the Co-operative Housing Society and MHADA in the form of built-
up area, as given in Table No.7-D below and the share of MHADA shall be handed over to
MHADA free of cost.
To see how Table 7-C and the rest of UDCPR apply to a particular plot, with the clause behind every figure, open Citiwise.
The text of the Unified Development Control and Promotion Regulations for Maharashtra State, as amended to 30.01.2025. The notification of the Urban Development Department, Government of Maharashtra, is the authoritative text.