UDCPR 2020 / Chapter 2, Development permission and commencement certificate
2.2 Procedure for obtaining development permission / building
UDCPR 2020 as amended to 30.01.2025
PERMISSION / COMMENCEMENT CERTIFICATE
Under this regulation
- 2.2.1 Notice / Application
- 2.2.2 Information Accompanying Notice / Application
- 2.2.3 Ownership title and area
- 2.2.4 Key Plan or location plan
- 2.2.5 (a) Sub-division / Layout plan
- 2.2.6 Site Plan
- 2.2.7 Building plan
- 2.2.8 Building plans for Special Buildings
- 2.2.9 Service plan - Plans, elevations and sections of water / grey-water supply, sewage
- 2.2.10 Supervision
- 2.2.11 Clearance from other Departments
- 2.2.12 Building / Layout Permission Scrutiny Fee
- 2.2.13 Development Charges
- 2.2.14 Premium Charges and Fire Infrastructure Charges.
- 2.2.15 Structural Stability Certificate
- 2.2.16 Signing the Plan
- 2.2.17 Size of Drawing sheets
- 2.2.18 Colouring Notations for Plans
- 2.2.19 Qualification and Competence of the Architect / Licensed Engineer / Structural Engineer /